• First Street Progress
  • St. Charles Police Department Urges You to Talk to Your Teen about Safe Driving for Prom and Graduation Season

Latest News

Work to Begin June 1 and Continue through the Summer 5/27/2016
Parade Steps Off at 10 a.m. at 6th & Main Streets 5/26/2016
Rates Include New Fee for State-Mandated Regulation Compliance 5/25/2016
Maintenance to Last Three Weeks 5/24/2016

Project News

New Water Tower at Red Gate Road and IL Rt. 25

Update - 5/31/16

Last week, CBI applied the finish coat to the exterior bowl, as well the finish coat to the interior wet and interior dry base cone. 

5/31/2016
Tyler Road & Illinois Bridge Work Closures
Work to Begin June 1 and Continue through the Summer

The City of St. Charles is launching two road construction projects on South Tyler and repairing the Illinois Bridge. All three projects are scheduled to begin June 1 and continue through the summer.

5/27/2016

South Tyler Road Rehabilitation Project

Update - 5/26/16

Construction is scheduled to start the week of 5/31/16.

5/26/2016

Illinois Bridge Repair Project

Update - 5/26/16

The Illinois Bridge Repair project is scheduled to begin the week of May 31st.  During construction the roadway will be reduced to one lane in each direction from Riverside Avenue to First Street.    Updates for this project will be minimal as the work will be confined to one

5/26/2016

North 5th Avenue (Route 25) Water Main Replacement Project

Update - 5/23/16

The Contractor will be on site working on punch list items this week.

5/23/2016