Update - 9/29/22

During the week of October 3rd, the contractor will be finishing up all the underground water and sanitary pipe work and will begin the road restoration; the first part of this restoration will be the concrete curb and driveway approaches. 

Update - 9/9/22

On Saturday, September 9, a crew will start grading for the new curb and roadway near the railroad tracks, slowly working north. 

Sewer crews will continue to install sewer main to the north during the week of September 12.  The Sewer crew is expected to be near the intersection of Rte. 64 and Kautz Road at the end of the week. 

 

Update - 7/29/22

The Riverside Lift Station Project is underway and the Jones Law Office has been moved.  New sidewalk to the law office was installed, and over the next several weeks, deteriorating wood on the Jones Law Office will be repaired.  

The contractor will be starting the excavation for the new lift station. 