Fire Station #1 Construction Project
|
Fire Station 1 Project Webcam
Project News |
Project Photos |
- Oct. 31, 2008 - In the last two weeks, a construction fence and visibility barrier has been installed around the project site. The sidewalk on the east side of First Avenue, between Cedar and State has been closed. The street signs and several trees have been removed in order to facilitate this site work.
Interior demolition has been progressing rapidly with substantial progress in the basement, first and second floors. The City of St. Charles Fire Department and Public Works Department has meet with the Downtown Partnership to consult on a signage plan for future road closures.
Site work plans for next week include the excavation of the parking lot and work on the retaining wall. A WebCam has been installed on City Hall and will soon be available to view online.
- October 14 , 2008 - The project groundbreaking ceremony took place Tuesady, October 14, 2008.
|
|
| PROJECT OVERVIEW |
| Name: |
Fire Station #1 |
| Overview: |
7,000 square foot three-bay apparatus structure in conjunction with the renovation of 17,000 square feet of adjoining office space contained within a three-story building in the downtown, historic preservation district. |
| Status: |
Contract awarded to Williams Construction Management.
|
| City Contact: |
Joe Schelstreet, Assistant Fire Chief, 630-762-6984 |
 |
|