The project bids are scheduled to be opened the fourth week of April 2012.  Construction is anticipated to commence in mid to late May of 2012.  All residents that are within the affected construction limits will receive a master notification letter describing the projects limits, and anticipated work activities.  This letter is typically released once the bidding results have been completed and approved.  The following streets are tentatively scheduled for the 2012 MFT Street Rehabilitation Project:

Street NameFromTo
Horne St.12th St.13th St.
Horne St.13th St.Marie St.
Horne St.Marie St. 14th St.
Marie St.Horne St.South End
N. 5th St.State St.Cedar St.
Cedar St.N. 7th St.N. 6th St.
Cedar St.N. 6th St.N. 5th St.
Cedar St.N. 5th St.N. 4th St.
Cedar St.N. 4th St.N. 3rd St.
Cedar St.N. 3rd St.N. 2nd St.
Katharine Ave.Prairie St.Horne St.
S. 7th Ct.Fellows St.Gray St.
Thornhill FarmMeadow Dr.Kildeer Ln.
Thornhill FarmKildeer Ln.IL Rte. 31
Madison Ave.S. 6th Ave.Jackson Ave.
Madison Ave.Jackson Ave.Monroe Ave.
Madison Ave.Monroe Ave.VanBuren Ave.
Madison Ave.VanBuren Ave.S. 7th Ave.
S. 12th St.Horne St.Fellows St.