Week of August 27, 2012
The Contractor will continue the transferring of water services on the new water main installed near Dunham Road heading east on East Main Street for approximately 1000 feet. This work is expected to be completed by the end of the week. Local businesses may experience temporary water shut-offs during this time. Public Works crews will be providing additional notification prior to these interruptions.
To read the full update, download the attached document.