Week of July 21, 2014

Phase One utility repairs have been completed on all streets.

Phase Two curb and sidewalk repairs are being completed on Ash Street, Kehoe Drive, Alice Court, Margaret Court, McKinley Street and Ohio Avenue.

Phase Three pavement replacement has been completed on Frontage Road, Squire Lane, Foxfield Drive, Lakeside Drive and the alleys, and is planned for Ash Street, Kehoe Drive, Alice Court, Margaret Court, McKinley Street, Ohio Avenue and Alleys this week.

Parkway restoration is taking place in the Cambridge East neighborhood.

 