West Side of Fox River
Avalon Court
Paving complete, Restoration September 1st.
8th Street and 8th Court
Paving complete, Restoration September 1st.
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Paving complete, Restoration September 1st.
East Side of Fox River
Walnut Ave.
No work this week.
Crabapple Ln.
Paving complete, Restoration September 1st.
S. 10th Ave.
No work this week.
Stone Dr. and DuKane Dr.
Utility work in street. (Replacement of water main and storm sewer structures)
Tyler Road
No work this week.