The work completed for the week ending August 15, 2015 included the connection at Marion Avenue.  The contractor televised a section of the watermain for investigation of debris and performed heavy cleaning of the watermain using a swabbing device.  Cleanup efforts on the project site continue.

The scheduled work for the week ending August 22, 2015 will include the re-televising of the watermain prior to flushing and pressure testing to assure that the line has been cleaned thoroughly. 

The contractor will provide notifications to those residents affected by construction who may have restricted access to their driveways during this work 48 hours in advance.

All work schedules are weather dependent.  Daily lane closures should be expected on IL Route 25 for the above work this week.