Week of October 26, 2015

The work completed for the week ending October 24, 2015 included pressure testing of the new watermain from the Q Center south to the cemetery. 

The scheduled work for the week ending October 31, 2015 will include chlorination of the line from the Q Center south to the cemetery, inspection of new hydrants as well as flushing and testing of the new watermain from the cemetery south to just south of Allen Lane.  Once the pressure test is complete, chlorination and sampling of this line will be performed. 

All work schedules are weather dependent.  Daily lane closures should be expected on IL Route 25 for the above work this week.