2012 Concrete Roadway Construction - South 4th Street Reconstruction Roadway construction on South 4th Street from Prairie Street to Horne Street is anticipated to commence in mid - May of 2012 with anticipated completion date of July 1, 2012. Project will include Portland Cement Concrete pavement removal and replacement, curb and gutter removal and replacement, 6” water main and water service installation, sanitary and storm sewer manhole removal and replacement and parkway restoration. |
2012 Street Rehabilitation Program Construction on the 2012 Street Rehabilitation Project is anticipated to commence in late May 2012. The project will include hot mix asphalt pavement removal and replacement, curb and gutter removal and replacement, sanitary and storm sewer removal and replacement, parkway restoration and other appurtenant work for a complete improvement.
|
Il Rt. 64 and Oak Street Traffic Signal Installation This project entails the installation of a new traffic signal at the intersection of IL Route 64 and Oak Street including new storm sewers, sidewalks, curbs in addition to widening and resurfacing of the roadway.
Various temporary lane closures will be necessary to complete the storm sewer crossings so caution should be used when driving through the site.
Updates on the project will be provided on a weekly basis so please check back regularly. |
IL Rte. 64 from 7th Avenue to IL Rte. 59 Roadway widening to 6 lanes and intersection. Illinois Department of Transportation's Route 64 Project Page:  |
Red Gate Bridge  |
Sanitary Sewer / Watermain Project IL 64/East Main Street from 7th Avenue to Dunham Road
This project entails the replacement of the existing sanitary sewer on IL Route 64 between 7th Avenue and Hunt Club Road and the existing water main on N. 9th Avenue between IL Route 64 and Cedar Avenue, S. 13th Street between IL Route 64 and Indiana Avenue, Cedar Avenue between IL Route 64 and N. 9th Avenue, and Indiana Avenue between S. 13th Street and the dead end to the east. |
St. Charles Riverwalk - Bob Leonard Way (Brownstone Segment) Construction on the St. Charles Riverwalk - Bob Leonard Way (Brownstone Segment) is anticipated to commence in mid - July of 2012 with an anticipated completion date of mid – September 2012. Project includes the reconstruction of existing walkway to a brick paver walkway, regrading, bank stabilization, tree removal, excavation, concrete curb, erosion control and landscaping improvements. |