Walnut Drive: Phase 2 Project Update Final November 8, 2011 (02/07/2012)
ALamp Concrete has completed all remaining concrete curb, sidewalks, pavement and restoration. Project has been substantially completed with only minor punch list items, still outstanding. |
Sanitary Sewer / Watermain Project Project Update November 14, 2011 (02/07/2012)
Once the chlorination lab results are acceptable and the Illinois Environmental Protection Agency approves them, the new mains will be connected to the existing water mains and any fire suppression and domestic water services will be connected. The remainder of the disturbed pavement will be patched, various curb and gutter and sidewalks will be replaced and restoration of all grassy areas will begin as well. |
Illinois Ave & 38th Ave Reconstruction Project Update Final November 8, 2011 (02/07/2012)
ALamp Concrete has completed all remaining new concrete pavement on Illinois and 38th Avenue and all area streets are open to regular traffic. Project has been substantially completed with only minor punch list items, still outstanding. |
IL Rt. 64/Oak Street Intersection Improvement Project Update November 8, 2011 (02/07/2012)
Due to seasonal constraints, this project will be postponed until Spring 2012. This project will be updated when more information becomes available. |
2012 Street Rehab Program 2012 Street Rehabilitation Project (02/07/2012)
The project bids are scheduled to be opened the fourth week of April 2012. |