Update - 10/17/23
On Tuesday, October 17, the portion of Riverside Avenue (IL Rt. 25) that was impacted by the Riverside Lift Station Project was re-opened.
On Tuesday, October 17, the portion of Riverside Avenue (IL Rt. 25) that was impacted by the Riverside Lift Station Project was re-opened.
Week of October 16
Monday, 10/16/23 - Curb and sidewalk poured adjacent to the pavement replacement
Tuesday, 10/17/23 - Concrete pours in the prepared roadways sections.
Wednesday, 10/28/23 - additional pour if needed
Three days required for concrete to set-up
Week of October 23
Monday, 10/23 - remove curb, sidewalk and pavement
The work on all streets for this project has been substantially completed. The Contractor will be continuing to perform final cleanup, landscaping, and other minor “punchlist” tasks in the upcoming weeks.
Please see attached document on the right side of this project page for lawn care recommendations after construction.
East Side Streets
East Side Streets
East Side Streets
Base reclamation work to begin on Monday 8/14/23. See below for detailed construction schedule. Please do not park on the street once the pavement has been removed.
Pavement milling on Lexington/Liberty/Lancaster/Cranbrook and Hampton Course is scheduled to start the week of 8/14. Please check the website regularly for updates.
East Side Streets