Update - 8/29/19
Work on the Tenth Street Water Tower is scheduled to begin on Tuesday, September 10.
Work on the Tenth Street Water Tower is scheduled to begin on Tuesday, September 10.
All Streets are receiving final landscaping and punchlist work.
Anticipated construction work for the week of August 19 - August 23
Illinois, Cedar, State, Deville and Gray Streets - Roadway fabric and final asphalt
Illinois and Fieldgate - Striping
General Clean up
This week the contractor will be pouring concrete curbs and sidewalks, paving the asphalt binder course and adjusting structures in the roadway. Next week the contractor will complete the asphalt surface course. Landscape restoration will be ongoing.
Update 8/05/19 – Anticipated construction work for the week of August 5-9
East Side Streets
West Side Streets
Anticipated construction work for the week of July 29- August 2
East Side Streets
West Side Streets
The storm sewer replacement work is complete. The contractor is working on clean up and site preparation in the rear yards of Matisse Drive this week for the landscape restoration which is scheduled for next week. Tree replanting will take place in early fall when the weather is more suitable for a successful transplant.
Next week the contractor will begin landscape restoration and install the new cured-in-place liner on the old sanitary sewer main. Landscape restoration and contract punch list items will continue into early August.
Anticipated construction work for the week of July 22-26:
East Side Streets
West Side Streets