Week of August 11, 2014
Phase Two curb and sidewalk repairs have completed on all streets except Ohio Avenue.
Phase Three pavement replacement has been completed on all streets.
Phase Two curb and sidewalk repairs have completed on all streets except Ohio Avenue.
Phase Three pavement replacement has been completed on all streets.
The schedule of work for the week of August 4 is as follows:
Watermain work will begin Monday or Tuesday at the south end of the parking lot and will proceed north. This work is expected to take approximately three days.
The Fire Hydrant at State and Riverside is going to be relocated during the middle of the week.
We are anticipating the installation of electric pipe crossing on Riverside Avenue at State Avenue during the middle to the end of the week. The road will be open with partial lane closures.
Storm sewer improvements will begin at the end of the week.
Phase One utility repairs have been completed on all streets.
Phase Two curb and sidewalk repairs have completed on all streets except Ohio Avenue.
The Municipal Parking Lot Reconstruction is underway. As with any construction project, things must happen in sequential order and coordination between utilities and sub-contractors is critical. A project of this type will be very active on certain days and not so much on others. Keeping that in mind, the following schedule is what we know to be taking place for the remainder of the week of July 28. The overall project is not delayed and is anticipated to be open by Scarecrow Festival.
Beginning the week of July 21, construction fencing is to be installed and pavement is to be removed in preparation of utility repairs and site grading. The parking lot will be closed between City Hall and the Police Station as of Monday July 21.
The US Mail and utility bill drop boxes have been temporary relocated north of the intersection of North Riverside Ave. and State Ave. Links to “Temporary Drop Box Location” and “Downtown Parking Map” are available under Project Documents.
Phase One utility repairs have been completed on all streets.
Phase Two curb and sidewalk repairs are being completed on Ash Street, Kehoe Drive, Alice Court, Margaret Court, McKinley Street and Ohio Avenue.
Phase One utility repairs have been completed on Ash Street and Ohio Avenue, and are continuing on McKinley Street this week.
Phase One utility repairs are being completed on Ash Street and Ohio Avenue, and are planned for McKinley Street this week.
Phase Two curb and sidewalk repairs are in progress on Foxfield Drive and Lakeside Drive this week.
The Tyler Road Pavement Resurfacing Project has been awarded to Geneva Construction Company, Aurora, IL. The limits of this project are from East Main Street to Kirk Road. The placing of traffic control is scheduled to begin on Monday July 7, with the start of construction planned for Monday July 14.
Phase One utility repairs have been completed on Squire Lane, Foxfield Drive, Frontage Road, Kehoe Street, Alice Court and Margaret Court, and are in progress on Ash Street, McKinley Street and Ohio Avenue this week.