Week of July 27, 2015

West Side of Fox River

Avalon Court
Hot Mix Asphalt, leveling binder and crack prevention material

8th Street and 8th Court
Hot Mix Asphalt, leveling binder and crack prevention material               

Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Hot Mix Asphalt, surface and crack prevention material

East Side of Fox River

Walnut Ave.
Concrete street repair and patching

Week of July 27, 2015

The work completed for the week ending July 25, 2015 included the Allen Lane connection as well as the fire hydrant installation at this location. The connection at North Avenue was also completed with the associated fire hydrant.  Flushing and pressure testing of the new watermain has not yet been scheduled due to delivery of needed parts. Contractor has begun restoration of curb and gutter.

Week of July 20, 2015

The work completed for the week ending July 18, 2015 included fire hydrant installation at Allen Lane on 5th Avenue. Connections were also completed this week at connections at Delnor, private drive and Marion.  Flushing and pressure testing of the new watermain has not yet been scheduled due to delivery of needed parts.

Week of July 20, 2015

Work for the week of July 20 is scheduled as follows:

Concrete curb and sidewalk saw cutting, forming and pouring new concrete curb and sidewalks

Utility structure adjustments

Pavement grinding and pavement patching, mid-week through the end of the week

Week of July 20, 2015

West Side of Fox River

Avalon Court
Pavement Grinding, Pavement Patching and Driveway Apron Repairs

8th Street and 8th Court
Pavement Grinding, Pavement Patching and Driveway Apron Repairs                   

Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Pavement Grinding, Pavement Patching and Driveway Apron Repairs       

East Side of Fox River

Walnut Ave.
Utility work in street. (Replacement of water main structures)

Week of July 13, 2015

The work completed for the week ending July 11, 2015 included the continued installation of fire hydrants and valve vaults along 5th Avenue. The Stonehedge Road and North Avenue side street connections were also completed this week.  Flushing and pressure testing of the new watermain has been postponed until correct parts are obtained.

Week of July 13, 2015

WEST SIDE OF FOX RIVER

Avalon Court
Curb and sidewalk removal and replacement

8th Street and 8th Court
Curb and sidewalk removal and replacement
Utility work in street (Replacement of storm sewer structures)

Greenwood Lane, Mockingbird Court and Oxmoor Court
Curb and sidewalk removal and replacement

EAST SIDE OF FOX RIVER

Walnut Avenue
Utility work in street (Replacement of water main structures)

Crabapple Lane
Curb and sidewalk removal and replacement

Week of July 6, 2015

West Side Streets
Saw cutting started on west side streets the week of June 29. Storm sewer work started on Avalon Court the week of June 29 and has been completed.  Additional saw cutting, curb, sidewalk and utility repairs are scheduled to take place on west side streets the week of July 6. The affected streets are Greenwood Lane, Oxmoor Court, Mockingbird Court, Crabapple Lane, Avalon Court, South 8th Street and 8th Court.

East Side Streets
Saw cutting may be taking place on some east side streets the week of July 6.

N. Tyler Road
No work.

Week of July 6, 2015

The work completed for the week ending July 4, 2015 included the continued installation of fire hydrants and valve vaults along 5th Avenue. The Iroquois side street connection was also completed this week.  Flushing and pressure testing of the new watermain has been postponed until correct parts are obtained.

Week of June 29, 2015

The work completed for the week ending June 27, 2015 included removal of most steel plates in the roadway and replacement with temporary patching.  Fire hydrant installation continued on the 5th Avenue watermain heading south.  Due to the weather, flushing and pressure testing of the new watermain has been postponed to the week of June 28th.