Week of June 25, 2012

Most of the scheduled work has been completed and South 4th Street is currently open to traffic. Repairs of some sections of concrete pavement are anticipated to take place this week.

The contractor has been informed that emergency vehicles must have access to residential properties at all times.

All residents that are within the affected construction limits have received notification letters describing the projects limits, and anticipated work activities.