The Contractor will continue placement of the mainline bituminous sub-base for eastbound and westbound traffic from Powis Road towards Pheasant Run. This work is expected to be completed by Friday July 12, 2013.  Once this work is completed, the Contractor will begin preparing for the placement of the mainline concrete pavement for both eastbound and westbound traffic from Powis Road towards Pheasant Run. This work is expected to be completed by Monday, July 22, 2013.