Week of September 23, 2013

The Contractor is expecting to begin grinding the concrete roadway between Kirk Road and Kautz Road beginning Saturday, September 21, 2013, weather permitting.  Once the grinding work has been completed, the Contractor will place the first layer of asphalt material.  Once the installation of new traffic signal equipment is placed within the first layer of asphalt, the Contractor will return and place the final surface course and finalize all required striping.  This work is expected to be completed by October 4, 2013.