Week of October 1, 2013

Approximately 75 yards of concrete were poured this week,completing the walls on the second floor of the south part of the building. Interior painting took place in the truck dock, pump room, electrical room, storage room and stairs on the first floor. Equipment pads were also poured on the first floor of the building and seven pumps were put in place. Excavation and placement of a two inch water line and a two inch gas line were also completed, along with installation of new gas meter on the building.