Week of June 2, 2014

The main section of the biosolids and operational building is now completed. This section houses liquid storage, chemical storage, pumping and dewatering equipment along with the new Motor Control Center and plant power distribution. Equipment has been through start-up procedures with staff training. Most equipment is now operational and running on a daily basis.

The second section of the building that will house the maintenance area, garage and offices and has had the floors and bottom half of the walls poured. Backfilling and compaction is taking place around the building along preparation for sidewalk installation .