A Lamp anticipates to perform Seat Wall excavation and construction all week.  Monday, Tuesday and Wednesday will include installation of the irrigation system and sidewalk.  Concrete and brick work at Riverside and State is anticipated to be completed on Wednesday, and rough grading of the rain garden will take place on Thursday and Friday. 