Week of May 11, 2015

The work completed for the week ending May 8, 2015 included the continued installation of the watermain pipe along the east side of 5th Avenue from in front of 1560 – 1582 5th Ave.  The contractor began installation of watermain on the Q Center property Thursday, May 7th.

The scheduled work for the week ending May 16, 2015 is to continue to install the watermain pipe along the east side of 5th Ave, from in front of 1560 5th Ave, South to near Stonehedge Road. The contractor is also scheduled to begin connecting/installing the necessary bends, fire hydrants and valve vaults in the area of completed watermain on IL Route 25.  The contractor will also begin the installation of watermain on Allen Lane towards the end of the week.  The contractor will provide notifications to those residents on Allen Lane who may have restricted access to their driveways during this work 48 hours in advance.

All work schedules are weather dependent.  Daily lane closures should be expected on IL Route 25 for the above work this week.

created May 08, 2015 updated Mar 23, 2018