The work completed for the week ending July 25, 2015 included the Allen Lane connection as well as the fire hydrant installation at this location. The connection at North Avenue was also completed with the associated fire hydrant.  Flushing and pressure testing of the new watermain has not yet been scheduled due to delivery of needed parts. Contractor has begun restoration of curb and gutter.

The scheduled work for the week ending August 1, 2015 will include side street connections at Marion Avenue.  The contractor will continue with concrete work on driveway aprons and pavement patching.  The contractor will provide notifications to those residents affected by construction who may have restricted access to their driveways during this work 48 hours in advance.

All work schedules are weather dependent.  Daily lane closures should be expected on IL Route 25 for the above work this week.

 

 