Update - 01/09/18

Work on the site and the fence was completed in December of 2017.  In 2018, additional foundations for the electrical bus will be installed and equipment will start to be delivered.  The tap of the 35kV transmission line on Kirk Road is scheduled for February.  The goal is to have the substation serving load for the summer of 2018, and the project is currently on track.