2018 Street Rehabilitation Project Underway

The City of St. Charles has contracted with Schroeder Asphalt Services for 2018’s Street Rehabilitation Project.  This year’s project locations are as follows:

Street NameFromTo
Adams AvenueS. 9th AvenueEast End
Adams CourtAdams Avenue

End of cul-de-sac

Dover Hill CourtDover Hill RoadEnd of cul-de-sac
Fox Chase DriveN. Kirk RoadFoxfield Drive
Jackson AvenueSouth Avenue Washington Avenue
Jewel AvenueRuth AvenueS. 7th Avenue
Mildred AvenueRonzheimer AvenueRita Avenue

N. 12th Avenue

E. Main StreetWing Avenue
Persimmon Drive1315 Persimmon Dr.1345 Persimmon Dr.
Rita AvenueMildred AvenueS. Tyler Road
Ronzheimer AvenueS. Tyler RoadWeber Road

Ruth Avenue

Jewel AvenueS. 7th Avenue

Spring Avenue

S. 6th AvenueMonroe Avenue

Work is anticipated to start in early June.  All roadway work is scheduled to be completed in mid-August with parkway restoration to take place in September.  For residents on streets scheduled to be resurfaced, keep an eye out for a letter from Public Works with additional information.  If you receive an orange parking pass, work is anticipated to impact access to your driveway.

Please visit the 2018 Street Rehabilitation Program page on the City’s website at www.stcharlesil.gov/projects for construction updates for each street.  Look under 2018 Street Rehabilitation Program

updated Jun 12, 2018