11/26/18 Update

  1. Precast erection has begun.
  2. The asphalt patching on 14th and 17th Streets is complete. 
  3. The underground plumbing (excluding the garage area) is almost complete. This will give a good head start once the building is enclosed and make for a fast floor pour.
  4. The first phase of steel is ready for erection and the second is making its way to the structural steel subcontractors shop.