3/1/19 Update

  1. The majority of the north side of the building has glass. Winter protection is down, making the building look completely different.
  2. In-wall mechanical, electrical, and plumbing rough ins are ready for inspection on the west side. The drywall tops are on.
  3. The third concrete pour is finished so the stairwells now have floors.
  4. The east side of the first floor is being final graded and will be ready for concrete next week. 
  5. Construction of the detention are is moving at a very fast pace.

    