3/15/19 Update

1. We are ready for the last building related concrete pour. The first floor north east slab will be poured early next week.

2. The second floor drywall is ongoing and is working its way towards the east side. Offices, the IT area, and the administration desk area are taking form.

3. The first floor wall layout has started.

4. The main staircase and specialty railings have been measured, and those pieces should be on site within the next 3-4 weeks.

5. Block walls in the detention area are going up fast.