3/22/19 Update

1. The first floor east framing is wrapping up which will kickoff the west side next week. 

2. The west side concrete pour went well, which gets us ready for framing and MEP in wall work.

3. The detention area is almost complete. 

4. The housekeeping pads for the mechanical, electrical, and plumbing contractors have been poured and will soon be ready for their equipment in the mechanical and electrical rooms.

5. Drywall is ongoing upstairs on the second floor.