5/3/19 Update

1. The first floor drywall is roughly 80% complete. The taping crew will start efforts on the first floor while the flooring contractor takes over the second floor space.

2. The ceiling grid on the second floor is complete in a major portion of the second floor with the addition of light fixtures.

3. The north face of the elevator shaft is complete.

4. The accent tile in the bathrooms is on the mens locker room walls.

created May 08, 2019 updated May 08, 2019