5/10/19 Update

1. The main staircase stingers (sides) are in and the pans have been placed.

2. The main vestibule glass wall framing is installed and ready for glass.

3. The first floor lobby drywall has started with the south wall complete.

4. The men’s locker room and workout room flooring is complete.

5. The detention benches have been formed.

created May 13, 2019 updated May 13, 2019