7/12/19 Update

  1. The permanent fencing has started on the south side of the project. The temporary will remain for a short time until we have a substantial amount in place to keep a level of security.
  2. The rip rap (larger stone typically placed at various utility structures – in our case the pond inlets and outlets) has been placed at the pond and the native plugs have been holding nicely.
  3. The first and second phases of epoxy floors are complete. This includes the evidence garage and lab area.
  4. The above ceiling inspection in the main lobby and training room was successfully passed on Thursday which meant that ceiling tile could continue to be dropped in place.
  5. Interior finishes continue, including room signage and flooring on the first floor (photo of the elevator included)

 

created Jul 15, 2019 updated Jul 23, 2019