Update 7/02/20

Anticipated construction work for the week of July 6 – July 10

Please Note: All work contingent on weather

East Side Streets

  • N. 2nd Ave. – No work at this time
  • Edward Ave. – Landscape restoration, milling, possible asphalt work
  • ​​​​​​​Fox Glen Dr. – Landscape restoration, milling, possible asphalt work
  • ​​​​​​​King Richard Circle – Landscape restoration, milling, possible asphalt work
  • ​​​​​​​Queen Elizabeth Ct. - Landscape restoration, milling, possible asphalt work
  • ​​​​​​​Pinelands Rd. - No work at this time

West Side Streets

  • Fairview Dr. - No work at this time.
  • ​​​​​​​Heritage St./Ct. - Landscape restoration, milling, possible asphalt work
  • ​​​​​​​Horne St. – Utility repair work
  • ​​​​​​​Killdeer Ln. – Landscape restoration
  • ​​​​​​​S. 12th St. - No work at this time
  • ​​​​​​​S. 19th Street – No work at this time
  • ​​​​​​​Tradition Blvd. – Landscape restoration, milling, possible asphalt work