Update - 3/8/21

Anticipated construction work

Please Note: All work contingent on weather

Week of 3/15/21: Tree and brush removal

Week of 3/22/21: South Avenue to be closed at 7th Ave. for culvert replacement. The closure will last approximately 5 weeks.