Update - 3/26/21

Watermain installation crews have moved onto Production Drive, the water main installation will be proceeding west on Production Drive.

Additionally, drilling continues on Tyler Road under IL Rte. 64.  There will be continued traffic control and lane closures in this area.

City Crews will be installing additional valves to support the contractors work next week. There is one water shutdown that is scheduled for 3/29/21.

created Mar 26, 2021 updated Mar 29, 2021