Anticipated construction work for the week of May 17-21
Please Note: All work contingent on weather
- East Side Streets
- Fox Glen Drive – Concrete sidewalk pour may begin. Possible parkway restoration to begin.
- Fairfax Road – Concrete sidewalk pour may begin. Possible parkway restoration to begin.
- Forest Ridge Road – Concrete sidewalk pour may begin. Possible parkway restoration to begin.
- Hunt Club Drive – Possible parkway restoration to begin.
- S. 11th Avenue – Concrete sidewalk pour may begin. Underground utility work may begin. Possible parkway restoration to begin.
- S. 12th Avenue- Watermain work continuing
- S. 13th Avenue- Concrete sidewalk pour may begin. Underground utility work may begin. Possible parkway restoration to begin.
- Jewel Avenue – Concrete sidewalk pour may begin. Possible parkway restoration to begin.
- Jay Lane- Concrete sidewalk pour may begin. Possible parkway restoration to begin.
- West Side Streets
- Renaux Blvd. - Concrete sidewalk pour may begin. Possible parkway restoration to begin.
- St. Germain Place - Concrete sidewalk pour may begin. Possible parkway restoration to begin.
- Oak Street –
- N. 5th Street – Curb removal on E side of street to begin, curb pour to follow. Concrete sidewalk pour may begin. Underground utility work may begin.