Update - 6/10/21

Anticipated construction work for the week of June 14-18 

Please note:  All work contingent on weather

  • East Side Streets
    • Fox Glen Drive – Asphalt replacement to continue.
    • Fairfax Road – Asphalt replacement to continue.
    • Forest Ridge Road – Asphalt replacement to continue.
    • Hunt Club Drive – Asphalt replacement to continue.
    • S. 11th Avenue – Asphalt removal and replacement may begin.
    • S. 12th Avenue- Watermain work continuing  
    • S. 13th Avenue – Asphalt removal and replacement may begin.
    • Jewel Avenue – Asphalt removal and replacement may begin.
    • Jay Lane – Asphalt removal and replacement may begin.
  • West Side Streets
    • Renaux Blvd. – Asphalt replacement to continue.
    • St. Germain Place – Asphalt replacement to continue.
    • Oak Street – Asphalt replacement to continue.
    • N. 5th Street – Remaining concrete pours may begin. Asphalt removal and replacement may begin.