Update - 7/19/21

Anticipated construction work for the week of July 19 - July 23 

Please note:  All work contingent on weather 

  • East Side Streets
    • Fox Glen Drive – Complete
    • Fairfax Road – Complete
    • Forest Ridge Road – Complete
    • Hunt Club Drive – Complete
    • S. 11th Avenue – Asphalt surface to be placed
    • S. 12th Avenue – Asphalt surface to be placed, restoration may continue
    • S. 13th Avenue – Asphalt surface to be placed
    • Jewel Avenue – Road complete, restoration may continue
    • Jay Lane – Complete
  • West Side Streets
    • Renaux Blvd. – Complete
    • St. Germain Place – Complete
    • Oak Street – Pavement complete, traffic striping may begin.
    • N. 5th Street – Asphalt surface to be placed, restoration may continue
created Jul 19, 2021 updated Jul 19, 2021