Work anticipated week of 7/26/21
Please note all work is weather dependent
Begin retaining wall installation along the south side of Illinois Ave.
Permanent stabilization with seed and blanket between Indiana and Illinois Ave.
Grading and haul off north of Illinois Ave.
Concrete curb and gutter and sidewalk along Indiana Ave.