Update - 8/19/21

Anticipated work for week of 8/23 

Please note:  All work is weather dependent

Permanent restoration with seed and blanets along the creek banks 

Continue stone armoring along the creek banks 

Grading and place stone for bicycle path north of Illinois 

Framing and pouring concrete foundations for the pedestrian bridge at the north project limit 

Structure adjustments in the street on Indiana Avenue and Walnut Avenue 