Update - 8/27/21

Next week the Contractor will be installing sanitary sewer, storm sewer and water
main at the locations noted on the map. Additionally, new sanitary sewer
services will be constructed throughout the week for the following lots:


• 21 Roosevelt
• 25 Roosevelt
• 27 Roosevelt
• 29 Roosevelt
• 31 Roosevelt
• 33 Roosevelt
• 65 Roosevelt
• 83 Roosevelt


Residents at these addresses can maintain normal water use.

The intersection of Roosevelt and Elm will be closed Monday afternoon.

Construction is a moving operation; therefore, the work zones will change daily.
On-street parking will be prohibited in the work zone. Residents with driveways
within the active work zones are asked to relocate their car(s) to an available
location on Roosevelt Street or to a side street by 7 AM.

If you have any questions, please call Todd Wells with Engineering Enterprises,
Inc. at 773-454-4214 or City Department of Public Works at 630-377-4405.