Update - 11/2/21

Due to the weather forecast, please note the following schedule changes associated with the Roosevelt Street roadway improvements:

Week of 10/25/21
• Site clean up
• Restore driveway access

Week of 11/1/21
• Tuesday – Mill off existing pavement
• Wednesday – Install new asphalt binder course
• Thursday – Start structure adjustments

Week of 11/8/21
• Install new asphalt surface course.
• Start parkway restoration

As with all construction projects of this nature, schedules are weather dependent. We will do our best to notify you of any schedule changes due to inclement weather. If you have any questions, please call Todd Wells with Engineering Enterprises, Inc. at 773-454-4214 or City Department of Public Works at 630-377-4405.

 