You are here

Update 5/13/22

Update for the week of 5/16 - 5/20/22

  • Form and pour remainder of curb and gutter
  • Form and pour sidewalk
  • Milling pavement on 17th, Foundry, and Dean
  • Stone removal on Marguerite. Any impacted businesses will receive temporary access ramps.

 

created May 13, 2022 updated May 13, 2022