Anticipated work for the week of 5/23 - 5/27/22

  • Grading along sidewalk
  • Patching asphalt base on Dean, 17th and Foundry
  • Prime coat (oil) and asphalt binder of Marguerite
  • Prime coat (oil) and asphalt level binder on Dean, 17th and Foundry 