Anticipated construction work for the week of May 30 – June 3
Please Note: All work contingent on weather
No work will take place on the Memorial Day holiday
• East Side Streets
o Illinois Ave. 3rd to 10th – No work
o Illinois Ave. 38th to Kautz – No work
o Cumberland Green – No work
o Cumberland Pkwy. – No work
o N. 2nd Ave. – No work
o N. 3rd Ave. – No work
• West Side Streets
o S. 2nd St. – Utility work including scheduled water shutdown
o N. 4th St./Mark St. – No work
o S. 7th St. – Utility work may begin
o S. 14th St. – Curb/sidewalk removal and replacement
o S. 15th Ct. – Curb/sidewalk removal and replacement
o McKinley St. – Utility work including scheduled water shutdown. Curb/sidewalk removal and replacement
o Pleasant Plains – Curb/sidewalk removal and replacement
o Tower Hill Dr. – Curb/sidewalk removal and replacement
o Millington Way – Cleanup
o Matisse Dr. – Curb replacement
o Picasso Dr – Curb replacement
o Monet Pl. – Curb replacement