Please Note: All work contingent on weather
Milling and resurfacing work are currently on hold due to the Operator Union Local 150’s strike reducing stone material availability. Work will resume as soon as a resolution is reached.
No work will take place on 4th of July holiday.
East Side Streets
- Illinois Ave. 3rd to 10th – No work
- Illinois Ave. 38th to Kautz – No work
- Cumberland Green – No work
- Cumberland Pkwy. – No work
- N. 2nd Ave. – No work
- N. 3rd Ave. – No work
West Side Streets
- N. 3rd Ave. – No work
- S. 2nd St. – No work
- N. 4th St./Mark St. –Watermain shutdown scheduled for 6/27. Residents will be notified with a door hanger if they will be impacted by shutdowns.
- S. 7th St. – No work
- S. 14th St. – No work
- S. 15th Ct. – No work
- McKinley St. – No work
- Pleasant Plains – No work
- Tower Hill Dr. – No work
- Millington Way – No work
- Matisse Dr. – No work