Main Street Bridge North Sidewalk & Street Parking Spaces to Close

Work on Decorative Canopies Begins Oct. 28

The sidewalk and the adjacent street parking spaces on the Main Street Bridge over the Fox River will close while minor concrete repairs are made to the decorative canopies on the bridge. The north sidewalk and parking spaces will be closed for approximately two days, beginning Friday, Oct. 28, 2022, weather permitting. The sidewalk will reopen for the weekend and reclose to finish work on Monday. After work is complete on the north side, the south sidewalk and adjacent spaces will close for approximately three days for work. Vehicle traffic on the Main Street Bridge is not expected to be impacted.

updated Nov 14, 2022