Update - 5/8/23

This week work continues on the site investigation and construction fencing/site containment phase of the project.  Installation of additional signage, fencing and other pedestrian/traffic control features will be installed and work will begin on removal and salvage of brick pavers from both the existing east plaza and the roadway bricks for future use on this project and throughout the City.  Mobilization of steel and other materials for the new pedestrian ramp is expected in the next 7 to 10 days and demolition of the existing hardscapes (sidewalks, street and planters) is anticipated to commence shortly.

Please remember this site is open only to authorized personnel.  The City appreciates everyone’s patience while construction is happening and is looking forward to opening a wonderful new public space for all to enjoy. 