Update - 5/11/23

Anticipated construction for the week of May 15 - May 19 

Please Note: All work contingent on weather 

  • East Side Streets
    • Fox Chase Blvd. – No work
    • Hampton Course – Potential utility repairs / replacements
    • Lexington Ave. – Watermain work to begin in this neighborhood end of week
    • Lancaster Ave. – Watermain work to begin in this neighborhood end of week
    • Liberty Ave. – Watermain work to begin in this neighborhood end of week
    • Liberty Ct. – Watermain work to begin in this neighborhood end of week
    • Cranbrook Ave. – Watermain work to begin in this neighborhood end of week
  • West Side Streets
    • River View Dr. – Utility repairs / replacements
    • River Ridge Dr. – Utility repairs / replacements
    • Prairie Crossing Dr. – Utility repairs / replacements
    • Renard Ln. – Utility repairs / replacements
    • Voltaire Ln. – No work
    • Provence Dr./Ct. – Complete storm sewer and water work
    • Antoine Pl./Ct. – No work

 

created May 11, 2023 updated May 12, 2023