Update - 5/19/23

Update 5/18/23 – Anticipated construction work for the week of May 22 – May 27

Please Note: All work contingent on weather

East Side Streets

  • Fox Chase Blvd. – No work
  • Hampton Course – Potential utility repairs / replacements end of week
  • Lexington Ave. – Watermain work at intersection of Lexington and Cranbrook, storm sewer repairs. Water main work will include a scheduled shutdown on Monday 5/22.
  • Lancaster Ave. – No work
  • Liberty Ave. – Watermain installation from Cranbrook to north end
  • Liberty Ct. – No work
  • Cranbrook Ave. – Watermain installation starting at Lexington going to Liberty

West Side Streets

  • River View Dr. – Utility repairs / replacements
  • River Ridge Dr. – Utility repairs / replacements
  • Prairie Crossing Dr. – Utility repairs / replacements
  • Renard Ln. – Complete utility repairs / replacements
  • Voltaire Ln. – No work
  • Provence Dr./Ct. – No work
  • Antoine Pl./Ct. – No work