Project News

Update - 08/13/20

Anticipated construction work for the week of August 17 – August 21

Please Note: All work contingent on weather

East Side Streets

  • N. 2nd Ave. – No work at this time
  • Edward Ave. – No work at this time
  • Fox Glen Dr. – No work at this time
  • King Richard Circle – No work at this time
  • Queen Elizabeth Ct. - No work at this time
  • Pinelands Rd. - No work at this time

West Side Streets

Update 7/20/20

This week the contractor will directional drill the water main along the north leg of 2nd Avenue, and will begin preparing for the watermain installation along Delnor Avenue.

Update - 7/16/20

Anticipated construction work for the week of July 20 – July 24

Please Note: All work contingent on weather

East Side Streets

  • N. 2nd Ave. – No work at this time
  • Edward Ave. – Landscape restoration
  • Fox Glen Dr. – Landscape restoration, asphalt surface
  • King Richard Circle – Landscape restoration
  • Queen Elizabeth Ct. - Landscape restoration
  • Pinelands Rd. - No work at this time

West Side Streets

Update - 7/9/20

Anticipated construction work for the week of July 13 – July 17

Please Note: All work contingent on weather

East Side Streets

  • N. 2nd Ave. – No work at this time
  • Edward Ave. – Landscape restoration, structure adjustments, asphalt surface
  • Fox Glen Dr. – Landscape restoration, asphalt surface
  • King Richard Circle – Landscape restoration
  • Queen Elizabeth Ct. - Landscape restoration
  • Pinelands Rd. - No work at this time

West Side Streets

Update - 7/02/20

Next week the contractor will begin water main replacement.  Notice:  Mailbox bank will be installed and will be utilized beginning Monday, July 6th.  Existing mailboxes will be temporarily bagged/covered to eliminate confusion. 